Preparing a campaign

A campaign is a set of towers measured with the same procedure, usually one or more overhead lines. Everything the tool needs is described by one configuration file; the data live in a folder of your choice, for example:

campaign-2026/
├── config.json
├── grid_data.xlsx                    grid data per tower (updated by --calc)
├── measurement_description.xlsx      one row per measured tower
├── short_circuit_data.xlsx           short-circuit currents + line protection (optional)
├── measurements/                     all instrument files in ONE flat folder
│   ├── ZE_<line>_<tower>.xml
│   ├── UT_<line>_<tower>.txt
│   └── Map_<line>_<tower>.png
└── results/                          created by the tool

The quickest way to get a valid starting point is the demo campaign (gm-cli towers demo DIR): replace its files with yours and adjust config.json. gm-cli towers example-config config.json writes only the configuration.

Keep campaign data out of source repositories

Configuration and data contain names, locations and grid data. Keep them next to the measurements, not in a clone of a code repository (the groundmeas .gitignore excludes *.json, *.xml and *.csv for this reason).

Measurement files

All instrument files of a campaign are stored in one flat folder (directory.path_measurements). The file name tells the tool which line and tower a file belongs to.

File Instrument Required Content
ZE_<line>_<tower>.xml OMICRON COMPANO 100 yes fall-of-potential measurement and the measuring currents of the step/touch test
UT_<line>_<tower>.txt OMICRON HGT1 yes1 touch-voltage readings (StepTouch report)
ZE_<line>_<tower>_spez….xml COMPANO 100 no soil-resistivity measurement (any name that contains spez)
UT_<line>_<tower>-<neighbour>.txt HGT1 no voltage measured at the neighbouring tower during the injection at <tower>
Map_<line>_<tower>.<png\|jpg\|jpeg\|gif\|svg\|webp> – no map or sketch of the measurement layout for the protocol

Naming rules

  • Line identifiers must not contain _ – the underscore separates the parts of the file name. Hyphens, dots and digits are fine (L-110.07).
  • Tower identifiers may contain letters (28N, 2M). Leading zeros and letter case are ignored when files are matched: UT_L1_008n.txt belongs to ZE_L1_8N.xml.
  • Extensions are case-insensitive (.XML, .Txt).
  • Unicode spellings are normalised (macOS stores ü decomposed), so names with umlauts match on every operating system.
  • The layout of the COMPANO file names is configurable with directory.grounding_impedance_structure:
Value File name Example
PREFIX_LINENUMBER_TOWER (default) <prefix>_<line>_<tower>.xml ZE_LX-01_8.xml
LINENUMBER_TOWER <line>_<tower>.xml LX-01_8.xml
TOWER_LINENUMBER <tower>_<line>.xml 8_LX-01.xml

HGT1 reports are always named UT_<line>_<tower>.txt.

Delivery with one folder per tower

Contractors often deliver one folder per line and tower (<line>/Mast <tower>/…). gm-cli towers flatten copies such a delivery into the flat layout. Line and tower are taken from the folder names, so typos in delivered file names are corrected (UT_LH_01-0815_5.txt, a touch-voltage report saved as ZE_….txt); photos, PDFs and spreadsheets are not copied and the originals stay untouched.

$ gm-cli towers flatten delivery/ campaign-2026/measurements/
$ gm-cli towers flatten delivery/ campaign-2026/measurements/ --apply --report mapping.csv

Without --apply the command only prints the plan (N files, M renamed, K conflicts). If two files would get the same name it stops with exit code 1 and copies nothing. Folder names are matched with regular expressions (--line-pattern, default (LH[-_]\d+[-_][0-9A-Z]+), and --tower-pattern, default ^Mast\s+(\S+)); --only FOLDER (repeatable) restricts the run to some tower folders and --map-strip sets the prefix removed from the line in map file names (default LH-).

COMPANO 100 export (XML)

Export the measurement on the COMPANO 100 (or with its PC software) as XML. The tool reads

  • the potential-probe distances, the input voltages, the raw output currents and the corrected output currents of the fall-of-potential measurement (FallOfPotentialReport),
  • the output currents of the step/touch test (the current that was injected while the HGT1 readings were taken),
  • the nominal frequency configured on the instrument (available through the Python API; the evaluation uses nominal_frequency_Hz of the configuration),
  • for soil-resistivity exports the apparent specific resistances and the electrode distances a, b, c (SoilResistanceReport).

Units are converted to A, V and m (mA, µA/μA/uA, mV, µV, kV, cm, km and ft are accepted, see Units). A file that lacks one of the required elements is reported with its name and skipped. The readers are available as groundmeas.instruments.CompanoXMLReader and Hgt1TXTReader, see Import from OMICRON instruments.

HGT1 report (text)

The HGT1 StepTouch report is a tab-separated text file with a header row Location Meas. ID Date Time f1 Level1 f2 Level2 Termination followed by a unit row (levels in [V], [mV], [µV] or [kV], frequencies in [Hz]) and one row per reading. Each reading contains the voltage at two frequencies next to the power frequency (for example 30 Hz and 70 Hz); the value at the nominal frequency is interpolated linearly (see Physical background).

The Termination column tells how the voltage was measured:

Termination Meaning Used for the assessment with touch_voltage_evaluation
1k 1 kΩ measuring resistance (body impedance) only without_resistor
2x1k additional 1 kΩ in series (footwear/standing surface) with_resistor (default)

UTF-8 and Windows-1252 encoded files are both accepted.

Measurement description (measurement_description.xlsx)

One row per measured tower, describing how it was measured. The first worksheet is read.

Column Required Meaning
Leitung yes line identifier (as in the file names)
Mast yes tower identifier
Messung_RA_Profil_bool yes 1 if the footing-resistance profile of the COMPANO export is valid, 0 to ignore it2
Messung_RA_Einzelwert_Ohm yes (may be empty) footing resistance measured with a high-frequency earth tester in Ω
Entfernung_Hilfserder_m yes distance between tower and current electrode in m (needed for the 62 % method)
Messpunkte_UT yes measuring points of the touch voltage, comma-separated, e.g. Tower, Tower, Fence
Name, Vorname, Firma no measuring engineer and company (shown in the protocol)
Datum no date of the measurement
Winkel_Sonde_Hilfserder_grad no angle between potential probe and current electrode in degrees
Winkel_Leitung_Hilfserder_grad no angle between line and current electrode in degrees
Witterung no weather
Messtechnik_Name no instruments used
Messfehler_Z_pu, Messfehler_U_pu no measurement uncertainty of impedance and voltage (per unit)
Sichtbefund no visual inspection findings
latitude, longitude, altitude (or Breitengrad, Längengrad) no tower coordinates; used only by import-db for the location

Every column whose name equals a key of the JSON result is copied into the JSON file. Do not add columns named like computed results (for example UT_V), they would overwrite them.

Measuring points. Messpunkte_UT lists one entry per HGT1 reading, or one entry per measuring point if every point was measured twice (1k and 2x1k). If the HGT1 itself recorded real location names, those are used and a warning is logged when they differ from the description. If the number of entries fits neither, the list is repeated cyclically and a warning asks you to check the labels.

Grid data (grid_data.xlsx)

The grid values per tower. Only Leitung and Mast are needed initially; the --calc step fills in the rest and writes the workbook back (rows sorted, duplicates merged, further columns kept).

Column Unit Meaning
Mast, Leitung – tower and line identifier
Reduktionsfaktor – reduction factor \(r\) of the earth wire
Abschaltzeit s fault clearing time
Fehlerstrom A single-phase short-circuit current \(I_k\) at the tower
Lage_Prozent % position of the tower on the line (written by --calc)
Hinweis_Abschaltzeit – how the clearing time was determined (written by --calc)

The values are chosen per tower in this order (highest priority first):

Value 1. 2. 3. 4.
fault current flat value of the Leitungsschutz sheet short-circuit line model value in the workbook default_grid_data.fault_current_kA
reduction factor flat value of the Leitungsschutz sheet value in the workbook default_grid_data.r
clearing time Leitungsschutz sheet (position on the line) value in the workbook default_grid_data.tripping_time

Close the workbook and keep a backup

Excel locks open files; --calc then stops with a message. Because the workbook is rewritten, keep a copy of the original.

Short-circuit data (short_circuit_data.xlsx, optional)

One sheet per line

A worksheet named exactly like the line provides calculated single-phase short-circuit currents along the line, for example from a network calculation for faults at 0 %, 10 %, …, 100 % of the line length. Columns B to D are read; column A is free (e.g. the fault location in percent).

Column Header Meaning
B Ik short-circuit current in kA
C l distance of the fault location from the line start in km
D Mast tower number; only the first and the last row are needed (first and last tower of the line)

The tool fits the two-sided infeed model to these points and evaluates it at every measured tower. If the fit fails, a straight line is used and a warning is logged.

Sheet Leitungsschutz

Enables the position-dependent fault clearing time (and optional flat values per line). It is read only if line_protection.enabled is true in the configuration.

Column Required Meaning
Leitung yes line identifier
t_Schnellzeit_s yes clearing time in the middle section (both relays in zone 1), e.g. 0.1
t_Endbereich_s yes clearing time near the line ends (remote relay in zone 2), e.g. 0.4
Mast_Anfang, Mast_Ende for positions first and last tower number (0 % and 100 %)
Schnellzeit_von_Prozent, Schnellzeit_bis_Prozent no limits of the middle section, default 16 and 84
Fehlerstrom_pauschal_kA no flat fault current for the whole line
Reduktionsfaktor_pauschal no flat reduction factor for the whole line
Netzform, Schutzkonzept, Bemerkung no free text (network earthing, protection concept, remark)

Equal times in both columns give one flat clearing time for the line, e.g. a compensated network with t_Schnellzeit_s = t_Endbereich_s = 10. The background is explained in Assessment procedure.

Map_<line>_<tower>.<ext> is searched next to the JSON results first and then in the measurement folder; it appears on the first page of the protocol. A company logo for the protocol header is configured with the key logo.

Checklist

  • All files in one flat measurement folder, names follow the rules above
  • One row per tower in the measurement description, required columns present
  • Current-electrode distance filled in for every tower
  • Grid-data workbook closed in Excel, backup made
  • Short-circuit sheets named like the lines (if used)
  • Permissible touch-voltage curve checked against the applicable standard
  • gm-cli towers run --config … --calc runs without warnings

  1. A tower without HGT1 report is listed with a warning and skipped by the assessment, because the touch voltages are part of every protocol. ↩

  2. An empty cell counts as 1 (profile valid). ↩